Release Schedule 2: Choosing Distributions
Uses Only Free-Tier SpiceGrinder
Problem statement
The release has four tasks: design, build, test and docs. In the last lesson one triangle described design. We shouldn’t reach for the same shape every time: the right distribution depends on where an estimate comes from and on how that kind of work behaves when it goes wrong.
So the questions are: which distribution fits each task, and which task do we have to worry about?
The model
Four tasks, four reasons:
- Design is the designer’s three-point guess again: at best 5 days, most likely 8, at worst 15. A
Triangulartakes exactly those three numbers. - Build is work that overruns. It can’t take less than no time, and every so often it runs far past the plan. A
Lognormalhas that shape: a floor at zero and a long right tail. It’s set by its typical value, a median of 16 days, and asigmaof 0.4 for how wild the tail is. (SpiceGrinder takesmu, the log of the median: ln 16 = 2.7726.) - Test is another expert guess, so another
Triangular: 3, 5 and 12 days. - Docs is the one task with a history. We have the durations of the last 20 sprints, so we use them directly: an
Empiricaldraws from that list at random. (In Free the 20 values are written into the model; Pro’sFlatFilecan read them from a CSV instead.)
An Append puts the four side by side, one column per task, and for now each task is drawn independently. Lesson 4 adds the connections between them.
<?xml version="1.0" encoding="UTF-8"?>
<dataset columns="design, build, test, docs" seed="102">
<root node="Tasks"/>
<nodes>
<Triangular name="Design" min="5" mode="8" max="15"/>
<Lognormal name="Build" mu="2.772588722239781" sigma="0.4"/>
<Triangular name="Test" min="3" mode="5" max="12"/>
<Empirical name="Docs" values="5 6 6 7 7 7 8 8 9 9 6 5 10 12 7 6 8 14 7 6"/>
<Append name="Tasks">
<input name="Design"/>
<input name="Build"/>
<input name="Test"/>
<input name="Docs"/>
</Append>
</nodes>
</dataset>
Each row is one possible project: the days each of the four tasks takes. Run it a million times (about a second and a half) and look at the first rows (samples/simulation/task-distributions.xml in your own install, if you want to reproduce this; leave the seed at 102 and you get exactly these values):
grind --count 1000000 task-distributions.xml
6.399164102651392,34.09118610848373,8.334736067404226,12.0
8.32739827471821,12.550579870009901,4.127337989331635,8.0
13.944809347845812,20.33417405655924,6.212258116115994,7.0
11.99401171511139,17.14139250813068,11.644579051572022,9.0
Which task carries the spread
A task’s average tells you when it usually finishes. What it can do to the schedule depends on its spread, how far it wanders from that average:
| Task | Mean (days) | Spread (standard deviation) | Share of the project’s variance |
|---|---|---|---|
| Design | 9.3 | 2.1 | 7% |
| Build | 17.3 | 7.2 | 80% |
| Test | 6.7 | 1.9 | 6% |
| Docs | 7.6 | 2.2 | 8% |
The last column squares the spreads (that’s the variance) and compares them. For independent tasks the variances simply add up to the project’s total uncertainty, so a task with 3.5 times the spread of its neighbors has about 12 times the weight. Build has 3.5 times the spread of the others, and it carries 80% of the project’s uncertainty.
The companion page lets you slide Build’s sigma and watch its shape and its share change while the other three tasks stay exactly the same.
Two details bear noticing. Build’s tail is long: the typical run is 16 days, the mean is 17.3, one run in a hundred takes more than 40.6 days, and the longest in a million took 109.5. And Docs only ever produces eight different values (5, 6, 7, 8, 9, 10, 12 and 14), because that is all its history contains. An Empirical can’t invent a 20-day docs sprint. If you believe one could happen, the history is the limit, not the model.
Same mean, different tails
Build’s long tail raises a bigger question. If two distributions have the same average, how much does the shape of their tails matter? Insurance claims make the point sharply, because a few huge claims sit among many small ones. We’ll build two claim models with exactly the same mean of 10,000: a Lognormal with sigma 1, and a Pareto with a shape of 1.5, the classic heavy-tailed choice.
To make the means match exactly, solve for the parameters. A Lognormal’s mean is exp(mu + sigma² / 2), so for a mean of 10,000 and sigma 1, mu = ln(10,000) − 0.5 = 8.7103. A Pareto’s mean is shape × scale / (shape − 1), so scale = 10,000 × 0.5 / 1.5 = 3,333.33.
<Lognormal name="LognormalClaim" mu="8.710340371976184" sigma="1.0"/>
<Pareto name="ParetoClaim" scale="3333.3333333333335" shape="1.5"/>
Four million claims each (samples/simulation/claim-severity.xml, seed 1002):
| Lognormal | Pareto | |
|---|---|---|
| Mean | 9,994 | 9,963 |
| 99th percentile | 62,050 | 71,771 |
| 99.9th percentile | 132,765 | 332,581 |
| Share of all loss from the biggest 1% of claims | 9.2% | 21.2% |
An average can’t tell these two apart. The 99th percentiles differ by 16%, but the 99.9th percentiles differ by a factor of 2.5, and the Pareto’s biggest 1% of claims make up more than a fifth of everything paid. One more warning is built into the numbers: a Pareto with a shape of 2 or less has no finite variance, so its sample average (9,963 here, against a true 10,000) settles slowly, and you can’t trust a measured average of such data the way you can with the Lognormal’s.
Back to the schedule: Build is the task whose tail decides the risk. Choosing a Lognormal for it was a decision about how bad the bad days can get, and it’s the decision to revisit if the history says they get worse.
Check: do the numbers match the math?
Every figure above can be computed exactly:
- Design: (5 + 8 + 15) / 3 = 9.33 for the mean, and a spread of 2.10.
- Build: the mean is 16 × e^(0.4² / 2) = 17.33, the spread is 17.33 × √(e^(0.4²) − 1) = 7.22, and the 99th percentile 40.6 is 16 × e^(2.326 × 0.4).
- Test: (3 + 5 + 12) / 3 = 6.67, spread 1.93.
- Docs: the mean and spread of the 20 listed values, 7.65 and 2.22.
- Claims: the Lognormal’s 99th and 99.9th percentiles are
exp(mu + z × sigma), 62,112 and 133,329, with 9.2% of the loss in the top 1%. The Pareto’s arescale × 100^(1/shape)andscale × 1000^(1/shape), 71,814 and 333,333, with0.01^(1/3)= 21.5% of the loss in the top 1%.
Our million runs gave 9.33, 17.33, 6.67 and 7.65, spreads of 2.10, 7.22, 1.93 and 2.22, and a Build 99th percentile of 40.6. The claim percentiles land within 0.5% of theory, and the top-1% shares within 0.3 points; the Pareto’s 99.9th percentile is the hardest number to pin down, because the heavy tail makes it noisy.
What this gives you: a distribution chosen for a reason rather than by habit, a way to see which task actually drives the uncertainty (compare the variances), and a reminder that two models with the same average can carry very different risk in their tails.
One more thing the four tasks need before they are a project: how they connect. Design comes first, Build and Test run in sequence, and Docs runs alongside them. The next lesson turns the four columns into a finish day and asks how likely a given deadline is to be missed.